Bustamante Engineers Case Study: Goshen Commons Paving Project

BUSTAMANTE STAFF • September 20, 2024

Goshen Commons Paving Project

The BUSTAMANTE ENGINEERS project we are highlighting this month involved the asphalt milling and overlay of all internal roadways and parking areas within the residential condominium community, pavement line striping, inlet top replacement, curbing and flatwork replacements, downspout tie-ins to stormwater roadway inlets, and the installation of concrete dumpster pads.

Downspout Tie-in 

The internal building downspouts were outletting along the curbline of the parking areas located in front of the condominium buildings. This was considered a safety concern because it allowed water to pond on the pavement surface and could lead to freezing and icy conditions in the winter months.

Goshen Commons Paving Project 1

Stormwater System Tie-in

We decided the best course of action was to tie these downspouts into the internal roadway stormwater system to avoid stormwater runoff on the surface of the roads.

Goshen Commons Paving Project 2

Dumpster Pad

There was a total of seven concrete dumpster pads installed throughout the community. Two of the dumpster pads were extended to allow for the dump trucks to have access for removal. Control joints were placed in the concrete sections to account for the freeze/thaw cycle and to avoid major concrete cracking.

Goshen Commons Paving Project 3

Curbing, Sidewalk & Inlet Top Replacements 

Prior to construction, the contractor and engineer completed a walkthrough inspection to mark out locations where concrete replacements were necessary. This included concrete curbing, sidewalks, and stormwater inlet tops. These replacements should be completed prior to paving the new pavement surface to avoid heavy machinery driving on the new pavement surface.

Goshen Commons Paving Project 4

Milling of Pavement 

Once all of the downspout tie ins and concrete replacement work was completed, the milling of the pavement surface was ready to begin. The milling of the roadway consisted of removing the surface course layer of pavement which consisted of 2” of asphalt.

Goshen Commons Paving Project 5

Full Depth Restoration

After the roadways were milled, an inspection was completed to determine locations of poor base locations of the pavement. Typical signs of base failure include large cracks, and areas of settlement. These locations were saw cut and the pavement was removed down to the base layer of stone. Then the stone was compacted thoroughly, more stone was added if necessary. The binder course layer of pavement is paved prior to the surface course being applied.

Goshen Commons Paving Project 6

Overlay

Once all of the full depth restoration locations have been addressed. The roadways are ready to be paved. The surface course layer of pavement consists of 2” of 9.5mm HMA Superpave. Once the pavement is placed, rollers and hand tampers are used to compact the asphalt that is placed.

Goshen Commons Paving Project 7

All the Community Association Engineering Services You Need

Upon completion of the paving, one final punch out inspection is completed to determine any areas that need to be addressed prior to final payment authorization. The Engineer presents a final punch out report to the Contractor with the location of concern and direction for remediation. Once all punch items have been addressed the engineer presents a close out and a final payment review letter to the owner stating that the Contractor successfully completed the scope of work agreed upon in the contract and all payment applications are approved for payment.

Your Community Is Our Business

BUSTAMANTE ENGINEERS Inc begins every proposal or study with a thorough visit to your community. During our visit, we want to meet the key members of your community so we can best understand questions and concerns. We appreciate the subtleties of Community Associations and recognize the importance of personal contact and local knowledge. Our commitment is ongoing from the early planning stages through to maintenance and future improvements. If you, your community, or someone you know is looking to complete a project, please click to contact us or call 215-340-6990 today.

SHARE CONTENT

RECENT POSTS

When to Call in the Pros for a Structural Inspection
By BUSTAMANTE ENGINEERS STAFF August 1, 2025
A structural inspection is a close visual examination performed by a licensed engineer to assess the health of your home’s load-bearing components, such as the foundation, joists, trusses, columns, beams...
Five Things to Look for When Inspecting an Existing Deck
By BUSTAMANTE STAFF May 28, 2025
It is recommended to inspect your deck annually to identify any issues that need attention. To assess the deck’s overall safety and compliance with building codes, focus on the five key areas listed below...
Ice Dams Are Typically Caused by a Winter Heat Loss Problem
By BUSTAMANTE STAFF February 18, 2025
What Are Ice Dams? Ice dams are ridges of ice that form at the edge of a roof, preventing melted snow from properly draining off. This trapped water can seep under shingles and into your home, leading to leaks, mold growth, and structural damage.
Show More